Fund Type: Drain: True Balance: Loan Balances: Current Balance: |
2600 - General Drain Construction/Reconstruction 543R - J.H. Elliott 35,852.69
0.0035,852.69 |
|||||||||||
| Mth | Day | Year | Ref Num | To Whom | For What | Principal | Int/Pen | Collected | Assessment | Receipts | Disbursed | Balance |
| Jan | 12 | 2026 | W161842 | Crossroadds Bank Attn: Nathan Fansher | Drain Reconstruction | 9,168.23 | 35,852.69 | |||||
| Dec | 18 | 2025 | Q014534 | County Treasurer | 2025 Fall Settlement | 27,929.21 | 11.80 | 27,941.01 | 27,941.01 | 45,020.92 | ||
| Oct | 14 | 2025 | W160778 | Smith's Excavating | Drain Reconstruction | 750.00 | 17,079.91 | |||||
| Jul | 21 | 2025 | W153148 | Crossroadds Bank Attn: Nathan Fansher | Loan Payment | 1,681.81 | 17,829.91 | |||||
| Jun | 16 | 2025 | Q014073 | County Treasurer | 2025 Spring Settlement | 13,630.27 | 13,630.27 | 13,630.27 | 19,511.72 | |||
| Feb | 3 | 2025 | W151470 | Crossroads Bank | 1,217.50 | 5,881.45 | ||||||
| Jan | 21 | 2025 | W151417/151418 | Surveyor's Office | A Repayment to Fund 1158 | 12,988.18 | 7,098.95 | |||||
| Jan | 2 | 2025 | Q013652 | Crossroads Bank | Loan | 6,492.40 | 20,087.13 | |||||
| Dec | 20 | 2024 | Q013609 | County Treasurer | 2024 Fall Settlement | 7,207.13 | 7,207.13 | 7,207.13 | 13,594.73 | |||
| Oct | 2 | 2024 | W150241 | Smith's Excavating | Maintenance | 6,492.40 | 6,387.60 | |||||
| Sep | 27 | 2024 | Q013360 | Crossroads Bank | A Loan | 13,622.50 | 12,880.00 | |||||
| Sep | 23 | 2024 | W149792 | Banning Engineering | Maint | 742.50 | ( 742.50) | |||||
| Aug | 26 | 2024 | Q13258 | Surveyor's Office | A Loan from Fund 1158 | 1,138.81 | 0.00 | |||||
| Aug | 19 | 2024 | W149544 | Smith's Excavating | Maint | 45,438.80 | ( 1,138.81) | |||||
| Aug | 13 | 2024 | Q13228 | Crossroads Bank | Loan | 45,438.80 | 44,299.99 | |||||
| Apr | 8 | 2024 | W147902 | Banning Engineering | Engineering | 690.00 | ( 1,138.81) | |||||
| Mar | 18 | 2024 | Q12816 | Surveyor's Office | A Loan from Fund 1158 | 1,919.37 | ( 448.81) | |||||
| Mar | 4 | 2024 | W147542R | Banning Engineering | Engineering | 373.75 | ( 2,368.18) | |||||
| Mar | 4 | 2024 | W147612 | Paxton Media Grp / Wabash Plain Dealer | Advertising | 75.06 | ( 1,994.43) | |||||
| Mar | 4 | 2024 | W147542 | Banning Engineering | Engineering | ( 373.75) | ( 1,919.37) | |||||
| Mar | 4 | 2024 | W147542 | Banning Engineering | Engineering | 373.75 | ( 2,293.12) | |||||
| Jan | 22 | 2024 | W147172 | Paxton Media Grp / Wabash Plain Dealer | Advertising | 16.20 | ( 1,919.37) | |||||
| Jan | 8 | 2024 | W146930 | Banning Engineering | Maint | 702.50 | ( 1,903.17) | |||||
| Dec | 4 | 2023 | W146498 | Banning Engineering | Engineering | 253.75 | ( 1,200.67) | |||||
| Nov | 6 | 2023 | W146281 | Paxton Media Grp / Wabash Plain Dealer | Advertising | 16.92 | ( 946.92) | |||||
| Nov | 6 | 2023 | W146210 | Banning Engineering | Engineering | 761.25 | ( 930.00) | |||||
| Oct | 23 | 2023 | W146059 | Banning Engineering | Engineering | 168.75 | ( 168.75) | |||||
| Oct | 23 | 2023 | Q012395 | Surveyor's Office | A Loan from Fund 1158 | 482.50 | 0.00 | |||||
| Sep | 5 | 2023 | W145572 | Banning Engineering | Engineering | 482.50 | ( 482.50) | |||||
| Aug | 28 | 2023 | Q012247 | Surveyor's Office | A Loan from Fund 1158 | 9,447.50 | 0.00 | |||||
| Aug | 7 | 2023 | W145267 | Banning Engineering | Maint | 451.25 | ( 9,447.50) | |||||
| Jul | 24 | 2023 | W145112 | Banning Engineering | Maint | 4,120.00 | ( 8,996.25) | |||||
| Jun | 5 | 2023 | W144669 | Banning Engineering | Engineering | 4,876.25 | ( 4,876.25) | |||||